The way runs from Kapadia Nagar Junction adjacent LBS Road to the Western Express Highway astatine Vakola Junction. Passing done important points similar Vakola Junction, Ambedkar Chowk, University Junction, and BKC Junction, the way promises to heighten connectivity betwixt Kurla and the elevated roadworthy astatine Vakola.
The Santacruz Chembur Link Road (SCLR) Extension task is nearing completion, with lone 100 meters of suspension span near to install. This conception is portion of a cable-stayed bridge, and the last installation awaits 2 planned postulation blocks, pending indispensable permissions by the postulation police, an authoritative from the Mumbai Metropolitan Region Development Authority (MMRDA) said.
The installation volition beryllium phased to accommodate the stretch’s curvature, aft which suspension cables and roadworthy surfacing volition follow. With approvals successful place, the remaining agelong of the SCLR is acceptable to unfastened to the nationalist connected January 1, 2025.
Additionally, the Brihanmumbai Municipal Corporation (BMC) precocious completed a Rs 16 crore outgo to defence authorities for indispensable onshore acquisition related to the project.
This 4.2-kilometer SCLR hold was initially planned to decorativeness successful 2019 aft operation began successful 2016 but determination were delays owed to aggregate reasons, including defence onshore requirements.
The hold starts astatine Kapadia Nagar, extending to Panbai International School. The way runs from Kapadia Nagar Junction adjacent LBS Road to the Western Express Highway astatine Vakola Junction. Passing done important points similar Vakola Junction, Ambedkar Chowk, University Junction, and BKC Junction, the way promises to heighten connectivity betwixt Kurla and the elevated roadworthy astatine Vakola.